Google Building, Kings Cross, London
Development of 990,000 square feet over eleven floors
We fabricated fifty tonnes of balustrade brackets for Google’s first wholly-owned building outside of the U.S
All 4,566 brackets and washers were custom-made in epoxy weatherproofed resin and intumescent coating, giving ninety minutes of fire protection.
The project was completed in March 2023 within a four months timeframe at a total cost of £300,000.